TURNAROUNDQC ← Back to Turnaround QC
Free Resources

Blank turnaround QA/QC forms you can print today.

The fifty-one forms every turnaround crew ends up rebuilding in Excel at 0200 on day one — the QA/QC pack from weld log to mechanical completion, the package review and exchanger closure sheets, and the safety pack: permits, LOTO and gas test logs, lift plan, toolbox talk, incident report and inspections. Free, ungated, and printable as they are.

These are the same record structures Turnaround QC uses, so if you ever move off paper, nothing has to be re-thought.

Weld Log

TA-WL-01 · Rev 0

Nineteen welds against one isometric, each with its WPS, both welders — root and cap, because they are routinely two people — both heat numbers, and the date welded. That date is the column that earns its place: continuity, the WPS revision in force and the heat treatment window are all judged at the day the arc struck, not at today’s.

Open the form →Landscape

NDE Report

TA-NDE-01 · Rev 0

One examination, with the acceptance criterion as tick boxes rather than a ruled line. The same indication passes B31.3 Normal fluid service and fails Category M, so “Accept” with nothing beside it is not a result. The technician’s level and certification expiry sit next to the result rather than in a folder.

Open the form →Portrait

Heat Treatment Record

TA-PWHT-01 · Rev 0

Soak temperature and time, heating and cooling rates, thermocouple count and location, and the chart number. The chart is the evidence and this sheet is what points at it — a cycle recorded without its chart number cannot be checked against what the machine actually did.

Open the form →Portrait

PMI Record

TA-PMI-01 · Rev 0

What the specification called for against what the analyser found, on one component, with the heat number and the instrument. Two blanks that look redundant and are not: a sheet carrying only the alloy found is a sheet with nothing on it to disagree with.

Open the form →Portrait

Pressure Test Report

TA-PT-01 · Rev 0

Test pressure and hold time, pressures and temperatures at start and end, and two gauges of different ranges each with its calibration due date. One gauge is a reading; two is a check. The relief setting and the owner or third-party witness are on the same page.

Open the form →Portrait

Flange Joint Assembly Record

TA-FJ-01 · Rev 0

Gasket type, spec and lot, bolt spec and count, lubricant, pattern, target against final pass, and the tool that produced it with its calibration date. Broken by and made up by are two blanks, because they are two people on two shifts.

Open the form →Portrait

Blind List

TA-BL-01 · Rev 0

Nineteen blinds, each with its tag number, signed in and signed out. The removal columns are the sheet: every blind list in circulation records what went in, the removals get remembered, and a blind left in on start-up is the incident everybody in the trade can name.

Open the form →Landscape

Vessel Entry & Internal Inspection

TA-VE-01 · Rev 0

Atmosphere readings as three numbers rather than a “gas tested” tick, the condition found, and the damage mechanism it points to — sulfidation, under-deposit, amine SCC, HTHA. The last line is the foreign material check, signed by the last person out before the manway goes back on.

Open the form →Portrait

Mechanical Completion Certificate

TA-MC-01 · Rev 0

One system, its prerequisites — test packages, reinstatement walkdown, blind list reconciled, relief valves back in — and the A, B and C punch counts still open at the moment it is accepted. What the owner signs is “I accept this system with these items outstanding”, so the counts belong on the certificate.

Open the form →Portrait

Exchanger Closure Form

TA-EXC-01 · Rev 0

Which components were opened, whether each needed repair and who initialled it, then a signed release for every stage of closing it back up — bundle, channel head, floating or bell head, dollar plate, and the final acceptance. Twenty signatures on one sheet, because on a turnaround that is what an exchanger takes to put back.

Open the form →Portrait

Exchanger Hydrotest Form

TA-EXH-01 · Rev 0

Tube side and shell side are two tests on one sheet, each with its own method, pressure, medium, duration and two calibrated gauges, and each signed separately — because they are tested separately, and a bundle that passed its channel test with the shell untested is half an exchanger.

Open the form →Portrait

Exchanger Torque Sheet / Flange Log

TA-EXT-01 · Rev 1

The package’s flange log on the torque sheet: one row per bolted joint — flange number, size, gasket, bolt size, the final torque (no 30 / 60 / 90 %), the torque wrench number so it can be checked against the calibration log, the date, and the owner and contractor QC sign-offs. Twelve joints here, eighteen more on the continuation. Cold torque, hot torque and accepted as the status.

Open the form →Portrait

Torque Sheet / Flange Log Continuation

TA-EXT-02 · Rev 0

Joints 13 to 30 for a package whose flange log runs past the first sheet, numbered to carry on from it and signed again on its own page.

Open the form →Portrait

The torque tag that travels with the exchanger: channel cover, channel to shell, floating head and shell cover across the top, gasket, stud count, size and grade, length and final torque for each, and beneath them who performed every bolting task — gasket surfaces inspected through the hot torque at 250 to 400 °F on start-up.

Open the form →Portrait

Equipment Hydrotest Form

TA-EQH-01 · Rev 0

The vessel version of the exchanger hydrotest: tower, drum, reactor, tank or seal pot, the code the repair was made under, the repair signed complete, then one test — method, pressure, medium, duration, two calibrated gauges, fluids removed, gauge zeroed — accepted by contractor QC and inspection.

Open the form →Portrait

Work Package Review

TA-WP-01 · Rev 0

Work Package Final Review

TA-WP-04 · Rev 0

The finished package signed off by the same twelve reviewers who approved it at planning — process, operations, mechanical and QA/QC required, the rest as the package touches them — with a final review status. This is the sign-off the dashboard counts; the review cover sheet is the planning check.

Open the form →Portrait

The cover sheet on a job package: the four reviews every package needs and the eight it may, then the three facts that make it done — signed off, physically in hand, ready to turnover — and the custody transfer.

Open the form →Portrait

Work Package Checklist

TA-WP-02 · Rev 0

Twenty-three things a package has to carry before the outage — scope, drawings, torque sheet, closure form, BOM, blind list, lifting and heavy equipment plans, ITP, safety and rescue plans — with who owns each one and five approvals.

Open the form →Portrait

Work Package Scope of Work

TA-WP-03 · Rev 0

The job step by step in the order it happens — before the outage, during it, after start-up — then the materials, the specifications attached and the drawings. The third sheet of the package, behind the review and the checklist.

Open the form →Portrait

Welding Procedure Specification (WPS)

TA-WPS-01 · Rev 0

Every variable by its QW number on one page — joints, base and filler metals, positions, preheat and interpass, PWHT, shielding and backing gas, current, amps, volts, travel speed, heat input, and technique — with prepared, approved and owner-acceptance sign-offs.

Open the form →Portrait

WPS Joint Detail and Weld Layers

TA-WPS-01A · Rev 0

Sheet 2 of the WPS: a box to draw and dimension the joint — bevel, groove angle, root opening, land, thickness, backing — the QW-482 weld layer and pass table, and a tick list of the documents attached behind it: PQR, sketch, filler certs, PWHT and NDE procedures, WPQs.

Open the form →Portrait

Procedure Qualification Record (PQR)

TA-PQR-01 · Rev 0

The coupon as it was actually welded — the as-run variables rather than ranges — and what the tensiles and guided bends did to it, with the lab, the report number and the certification the WPS stands on.

Open the form →Portrait

Welder Qualification Record

TA-WPQ-01 · Rev 0

One welder, one process: the P and F number ranges, positions and thicknesses qualified, the backing, the dates that keep the qualification alive — qualified, last continuity, vision test — and who witnessed the coupon.

Open the form →Portrait

Fit-Up Inspection

TA-FU-01 · Rev 0

The joint before the root goes in: preparation method, bevel angle, root gap, land, hi-lo, preheat applied, the cleanliness and tack checks, and the inspector who accepted it. Once the joint is filled nobody can tell what the gap was.

Open the form →Portrait

Weld Repair Record

TA-WR-01 · Rev 0

One repair on one weld: the attempt number, the defect and where it was, how it was removed and the excavation NDE, the repair WPS and welder, the re-examination that cleared it, and the NCR if it raised one.

Open the form →Portrait

Hardness Test Record

TA-HRD-01 · Rev 0

Three readings on weld metal, HAZ or base metal after heat treatment, the method and units, against the maximum the spec allows — and whether it goes back in the furnace.

Open the form →Portrait

Thickness Reading Record

TA-UT-01 · Rev 0

One CML: nominal, previous and current readings against t-min, with the corrosion rate and remaining life that come of them, the method and instrument, and room for a sketch of where the reading was taken.

Open the form →Portrait

Exchanger Bundle Record

TA-EXB-01 · Rev 0

The bundle from pull to reinstall: cleaning method, condition found, the eddy current reference, tubes plugged this outage against the total and the plugging limit, the bundle test and the gaskets renewed.

Open the form →Portrait

Repair / Alteration Record

TA-RA-01 · Rev 0

A code repair from classification to R-form: NBIC R-1 or R-2, the code basis and the engineering behind it, the weld, NDE, PWHT and test records it produced, the completion checks, and the Authorized Inspector who accepted it.

Open the form →Portrait

Relief Valve Service Record

TA-PSV-01 · Rev 0

One PSV out and back: set pressure, as-found pop and result, as-left pop, seat tightness, the seal or VR stamp, the bench report number, and the block valves car-sealed open behind it on reinstallation.

Open the form →Portrait

Reinstatement Walkdown

TA-RI-01 · Rev 0

The system walked down for start-up: blinds and joints counted in and out, valves in position, spec breaks verified, temporaries and strainers out, PSVs back and car-sealed, insulation restored — and both signatures.

Open the form →Portrait

Test Package Cover Sheet

TA-TP-01 · Rev 0

The package that goes on test: which isometrics, what medium and pressure under which code, the hold time, and the three things that have to be complete before the gauge goes on — welds, NDE, PWHT.

Open the form →Portrait

Flushing / Cleaning Record

TA-FC-01 · Rev 0

What went through the line — water, air, steam, chemical, pig — at what concentration and temperature, for how long, against what acceptance criterion, what the target screen caught, and where the effluent went.

Open the form →Portrait

Field Observation

TA-OBS-01 · Rev 0

Something seen in the field that is not yet a non-conformance: quality, safety, housekeeping or documentation, what was seen, what should happen about it, and who closed it.

Open the form →Portrait

Work Permit

TA-SF-00 · Rev 0

A general permit to work: what, where, who, the precautions ticked, the PPE, an atmospheric test if one is needed, signed out by the area authority and signed back in when the work is done.

Open the form →Portrait

Hot Work Permit

TA-SF-01 · Rev 0

Welding, cutting, grinding or open flame near live plant: the fire precautions ticked, the gas test and re-test frequency, the fire watch named and signed, and the watch time after the work stops.

Open the form →Portrait

Confined Space Entry Permit

TA-SF-02 · Rev 0

Entry into a vessel, tower or pit: isolation ticked, atmosphere tested before entry, ventilation and communication chosen, the attendant and the rescue method named — with the entrant log behind it.

Open the form →Portrait

Confined Space Entrant Log

TA-SF-02A · Rev 0

Who went in, when, and when they came out — kept at the hole by the attendant, with three in-and-out pairs per entrant and a re-test line at the foot.

Open the form →Landscape

Lockout / Tagout Log

TA-SF-03 · Rev 0

Every lock, tag and blind on the isolation: the energy source, the isolation point, the method, who applied it, who proved it dead by try-out, and who took it off.

Open the form →Landscape

Excavation Permit

TA-SF-04 · Rev 0

Digging near live plant: utilities located and hand-dug, the protective system chosen for the soil type, spoil set back, access every 25 ft, and the competent person named and signed.

Open the form →Portrait

Critical Lift Plan

TA-SF-05 · Rev 0

The load with its rigging and block weights, the crane configuration — boom, radius, counterweight — and the percent of chart, with the gear, the ground and the four people signed.

Open the form →Portrait

Toolbox Talk Sign-In

TA-SF-06 · Rev 0

The topic, the points covered, and twenty signatures from the people who were stood there. A tailgate talk whose sign-in sheet lives elsewhere is the one with nobody on it at the review.

Open the form →Portrait

Incident / Near-Miss Report

TA-SF-07 · Rev 0

What happened, to whom, where and when, classified; the immediate and root causes; the corrective actions; signed by the person who saw it and the two who own the fix.

Open the form →Portrait

Gas Test Log

TA-SF-08 · Rev 0

Every atmospheric test on the unit — where, when, O2, LEL, H2S and CO, the instrument and who held it, and whether the space was safe to enter.

Open the form →Landscape

Scaffold Inspection

TA-SF-09 · Rev 0

The twelve things a competent person looks at before the tag goes green — base, plumb, bracing, planking, rails, ties, load rating, clearance — and the tag colour that came of it.

Open the form →Portrait

Fall Protection Inspection

TA-SF-10 · Rev 0

Harness, lanyard and self-retracting lifeline checked item by item before anybody clips on — webbing, stitching, hardware, hooks, shock pack, labels — pass or fail per item.

Open the form →Portrait

Nonconformance Report

TA-NCR-01 · Rev 0

Discipline, severity, description, root cause, corrective and preventive action, disposition and closure — on one sheet, so the whole life of a finding is legible at a glance. How many welds or joints it reaches, and which code clause was missed, are blanks rather than an afterthought.

Open the form →Portrait

Request for Information

TA-RFI-01 · Rev 0

The question against the isometric, drawing or specification it refers to, with a response block and dates on both sides of it.

Open the form →Portrait

Punch List

TA-PL-01 · Rev 0

Nineteen rows for a walkdown, categorised by what blocks start-up, what blocks turnover, and what can be punched once the unit is back up — through to owner sign-off. That split is the whole negotiation, so it is categorised as it is raised.

Open the form →Landscape

Job Safety Analysis

TA-JSA-01 · Rev 0

For the pre-job briefing: permits including LOTO, line break, hot work, confined space, blinding and radiography, PPE through to SCBA and a chemical suit, eight step / hazard / control rows, emergency details, and a crew sign-on on the same sheet as the analysis. Isolation point and stored energy are two separate blanks, because answering the first is routinely mistaken for having answered the second.

Open the form →Portrait

JSA Continuation Sheet

TA-JSA-02 · Rev 0

Steps 9 through 16, for a job that needs more than the eight the JSA holds. The rows are numbered to carry on from the first sheet rather than restarting at one, so a step has the same number on paper as it does in the record. It repeats the JSA number, date and task at the top — a continuation page that gets separated from its parent on a jobsite has to be able to say what it belongs to — and it is signed again on its own page, because a page with no signature is one anybody could have added afterwards. The permits, PPE, isolation points and emergency details stay on sheet 1: those are decided once for the whole task, and asking twice is how you get two different answers.

Open the form →Portrait

Daily Report

TA-DR-01 · Rev 0

One day per sheet: crew on site and man-hours, work performed, equipment, materials and visitors. The delay cause is tick boxes with the hours lost beside it, because this is the sheet somebody reads two years later adding up what a cause cost — and “rain” written in a box is not a category.

Open the form →Portrait

Crew Timesheet

TA-CTS-01 · Rev 0

Eighteen rows, one person per day, against a cost code and system. Straight, overtime and double time are separate columns because they are paid and argued separately, and a single hours column loses the distinction at the one moment anybody needs it.

Open the form →Landscape

Turnaround Schedule

TA-PS-01 · Rev 0

Nineteen activities with planned against actual dates, percent complete and who owns each one — a sheet to walk down and mark up. An activity list, not a bar chart: no Gantt, and no float, which is a planner’s number recalculated by the tool that owns the logic and worse than useless written in pen.

Open the form →Landscape

Printing these properly

These forms are the easy part.

The hard part is what happens after they're filled in — the blind that went in on a sheet and came out on nobody's, the weld repair that was never re-examined, the gauge that expired between the calibration folder and the hydro, and the last four shifts of the outage spent assembling a turnover package out of a shipping container of paper and somebody's memory.

That's what Turnaround QC is for. Same records, but expiries, open NCRs and missing paperwork surface while you can still fix them, and the job book compiles itself.

See how it works →

A walkthrough of what actually goes in a turnover package is published, along with a spec quick reference and field notes. All free, and none of them behind a signup.

TURNAROUND QC QA/QC — DOCUMENT CONTROL SYSTEM Plans FAQs Contact Refund Policy