Mechanical Completion Certificate
One system, its prerequisites, and the A, B and C punch items still open at the moment it is accepted.
TURNAROUND QC
Turnaround QC
turnaroundqc.com
Project
Job No.
Client
Sheet ____ of ____
MC Certificate No.
System
Unit / Area
Date
Scope Covered
Prerequisites
Test packages complete and accepted
Yes
No
Reinstatement walkdown complete
Yes
No
Blind list reconciled against the tag board
Yes
No
Relief valves reinstalled, sealed and car-sealed
Yes
No
Documentation complete and in the turnover package
Yes
No
Punch items outstanding at acceptance
A — blocks start-up
B — blocks turnover
C — after start-up
Notes — conditions attached to acceptance
Contractor Signed By
Date
Owner Signed By
Date
Contractor / Date
QA/QC / Date
Owner Acceptance / Date