Test Package Cover Sheet
The package that goes on test: which isos, what medium and pressure, under which code, and the three things that have to be complete first.
TURNAROUND QC
Turnaround QC
turnaroundqc.com
Project
Job No.
Client
Sheet ____ of ____
Package No.
System
Unit / Area
Approved
Description
Isometrics Included
Medium
Hydrostatic - water
Hydrostatic - other
Pneumatic - air
Pneumatic - nitrogen
Service test
Sensitive leak test
Vacuum box
Initial service leak test
Design Pressure
Test Pressure
Hold Time
Code
ASME B31.3
ASME B31.1
ASME Section VIII Div 1
ASME Section I
API 570
Owner Spec
Pre-Test Readiness
Welds Complete
Yes
No
N/A
NDE Complete
Yes
No
N/A
PWHT Complete
Yes
No
N/A
Approved By
Status
Building
Assembled
Approved
Test Ready
Tested
Reinstated
Turned Over
Sign-Off
Contractor QC
Owner Inspector
Third Party
Print name
Signature
Date